Anaheim names a new city manager and approves a 20-year solar deal

The Anaheim City Council hired Oceanside's Jonathan Borrego as city manager and approved a 20-year purchase of solar and battery power. It also gave the long-delayed A-Town project in the Platinum Triangle a July 2027 deadline.

  1. 00:00 Headlines
  2. 00:35 Top story: Council hires Oceanside's Jonathan Borrego as city manager
  3. 01:47 Top story: Council approves 20-year deal for Fresno County solar and batteries
  4. 03:28 Top story: A-Town project gets a July 2027 deadline to rework its deal
  5. 05:28 Quick hits
  6. 07:36 Sign-off
Follow Anaheim onYouTube

Download the MP3 · 7.8 MB

This episode was produced with AI from the public recordings of the week's meetings. Links to the sources are in the show notes.

Transcript

Headlines

00:00

Maya This is CivicFM, with the week at Anaheim City Hall.

Maya Anaheim picks a new city manager, a familiar name coming back from Oceanside. Plus a twenty-year solar and battery power deal, and one more deadline for the long-delayed A-Town project.

Maya This episode was produced with AI from the public recordings of the week's meetings. Links to the sources are in the show notes.

Read more: Employment agreement for new City Manager · 20-year solar-plus-battery power purchase from Heartland Solar 1 · Deadline to amend or terminate the A-Town development agreement

Top story: Council hires Oceanside's Jonathan Borrego as city manager

00:35

Maya First up, a job that's been filled on an interim basis since February. On Tuesday the council voted seven to nothing to make Jonathan Borrego, now the city manager of Oceanside, Anaheim's next city manager. The job opened when Jim Vanderpool resigned in February. Greg Garcia, who had been assistant city manager, has served as interim city manager since late that month.

Theo Borrego isn't new here. The city's human resources director said Borrego spent twenty-nine years working for Anaheim, on projects including the Platinum Triangle vision and the Packing District.

Maya The director said a nationwide search by the firm CPS HR drew about a hundred sixty candidates, and the council interviewed finalists from California and out of state. One council member said he pulled the item from the consent calendar so the public could hear how the selection worked. He also credited the city's executive team for keeping things running during the vacancy.

Theo The contract sets a salary of four hundred nine thousand dollars, with severance that starts at twelve months and shrinks over time. Borrego takes over on December twenty-eighth.

Read more: Employment agreement for new City Manager

Top story: Council approves 20-year deal for Fresno County solar and batteries

01:47

Theo Our next story is about where Anaheim's electricity will come from for the next twenty years. The council unanimously approved a deal for Anaheim Public Utilities to buy all the power from a solar farm with battery storage in Fresno County. The city won't build or own the plant. It only buys what the plant produces.

Maya Staff called it the largest project in the utility's portfolio. The acting general manager said it helps meet the state's mandate of sixty percent renewable power by twenty-thirty. The battery stores cheap midday solar power for the evening, when demand and prices rise.

Theo By the agenda's numbers, it costs about forty-seven point seven million dollars a year on average, and roughly nine hundred fifty-five million over the twenty years. On Tuesday, staff rounded the yearly figure to about forty-seven million. Utility ratepayers pay for it, not the city's general fund.

Maya So will customers see it on their bills?

Theo Not in the near term, staff said. A Utah power plant goes offline in June twenty-twenty-seven, and this deal takes its place in the budget. Staff cautioned that future costs like transmission can't be predicted. They also acknowledged a gas plant would likely be cheaper without the state's rules, but new gas plants can't be built in California.

Maya One council member voiced frustration with state mandates that leave the city carrying an obligation this size. Council Member Natalie Rubalcava asked staff to consider lobbying Sacramento to relax them. Construction is expected to start in March twenty-twenty-seven, and the plant is expected to be running by summer twenty-twenty-eight.

Read more: 20-year solar-plus-battery power purchase from Heartland Solar 1

Top story: A-Town project gets a July 2027 deadline to rework its deal

03:28

Maya Our third story: the long-delayed A-Town project, on East Katella Avenue in the Platinum Triangle, got one more deadline. In September, the council found the project had missed a milestone in its development agreement, and that set up Tuesday's hearing.

Theo The Planning and Building Director said the developer, PT Metro, which is tied to Lennar, had trouble financing large podium projects and never pulled building permits for the last hundred thirty-two homes in this phase. The developer also missed a July deadline to apply for a formal amendment.

Maya The council set July thirty-first, twenty-twenty-seven as the date the agreement ends unless an amendment is adopted by then. Before the vote, the presiding officer noted that housing policy has changed since the project was first approved: some in-lieu fees are going up, and the city now has an affordable housing ordinance. Here's the question that followed, and staff's answer.

The presiding officer (from the meeting) Does any of that apply to this developer or is this developer grandfathered in because of this because of all the extensions we keep granting?

A speaker (from the meeting) As long as the development agreement is in effect, it locks in the playing field for the development.

Theo The director said the city's newer affordable housing and in-lieu fee requirements don't apply unless they're written into an amendment. The presiding officer predicted the project would show no progress by next July, and argued the city should stop letting developers extend agreements far into the future without keeping up with rising fees.

Maya Staff said it's making one final push for a deal that brings Platinum Triangle residents a grocery store. Council Member Natalie Meeks said that grocery store is why she would support the item. It passed six to one, with Mayor Ashleigh Aitken voting no. If no amendment is adopted by next July, staff said it would come back with an ordinance to end the agreement.

Read more: Deadline to amend or terminate the A-Town development agreement

Quick hits

05:28

Theo Now a few shorter items from Tuesday's meeting. The council started the process of giving Parking Company of America a franchise to run shuttles from Garden Grove hotels to the Disneyland Resort and the Convention Center. The shuttles fill the gap left when the Anaheim Transportation Network ended its ART bus service in March. The fare is eight dollars for an all-day pass, resort employees ride free, and staff confirmed the drivers are Teamsters. It passed seven to nothing. A public hearing on this franchise and two other shuttle franchises is set for December fifteenth.

Maya Also on the consent calendar was a three-year extension of the city's license with JR Wheels and Tires, a tire shop on city property on West Lincoln Avenue. The monthly fee rises from fifty-five hundred dollars to just over sixty-three hundred starting in December twenty-twenty-seven. Three public speakers called that far below market rent. It passed with the rest of the calendar, and Council Member Rubalcava recused herself on that item.

Theo The city attorney's office reported that, in closed session, the council approved a settlement in a lawsuit against the County of Orange and others. The settlement puts requirements on existing and future emergency shelters, and the city pays no money. The vote was five to nothing, with two members absent.

Maya Council members also asked staff for future reports. Council Member Natalie Meeks asked for an update on permit streamlining, Council Member Rubalcava asked for a memo on how a landfill strike could affect trash pickup, and Mayor Aitken asked for an agenda item on police overtime.

Theo Council Member Meeks announced a state grant of seven hundred fifty thousand dollars for a second emergency access road. It will serve a District 6 community of about three hundred homes that now has one narrow way in. She said the road should be finished in about a year and a half.

Maya And if you're at the public library, you may run into two replica mummies on loan from Guanajuato, Mexico. Council Member Rubalcava said they're rotating through city facilities.

Read more: Resort-area shuttle franchise for Parking Company of America · Consent calendar · Closed session report: a lawsuit settlement on emergency shelters · Council agenda setting · Council communications

Sign-off

07:36

Theo Before we go: if you spot something we got wrong, there's a link on the episode's page to tell us, and we read corrections on air.

Maya That's the news from City Hall. See you after the council's next meeting.

What happened

City Council Tuesday, November 10

13 items

The meeting's page · The recording · Agenda

Recognition of Loara Elementary School's Teacher of the Year

The council honored a Loara Elementary School teacher, a former 911 operator and Anaheim native, as the school's Teacher of the Year. 01:17:44

Write to the City Council about this

Recognition of the Miss Anaheim Beautiful Scholarship Program court

The council recognized the 2026-27 Miss Anaheim Beautiful titleholder and four teen ambassadors of the scholarship program. 01:24:57

Write to the City Council about this

Recognitions to be presented later

The clerk announced two recognitions to be presented at a later date: Law Enforcement Records and Support Personnel Week, and November 2026 as National Family Caregivers Month. 01:30:19

Write to the City Council about this

Council communications

Emergency preparednessImmigrants

Council members reported on district events and issues, including a state grant for a wildfire emergency access road in District 6, a weekend freeway closure, and a reminder about immigration enforcement activity. 02:41:49

  • Norma Campos Kurtz (Council Member, District 4) apologized for arriving late, explaining she was serving on jury duty. 02:42:02
  • Natalie Meeks (Council Member, District 6) addressed weekend gridlock in East Anaheim caused by a Caltrans closure of most of the eastbound 91 Freeway. 02:42:31
  • Natalie Meeks (Council Member, District 6) announced a $750,000 state grant, obtained through a state assemblyman's office, to build a second emergency access road for a community of about 300 homes with a single narrow access point. 02:43:38
  • Natalie Meeks (Council Member, District 6) said the access road project should be finished in about a year and a half. 02:44:42
  • A council member invited residents to a community resource fair and car show on Saturday at Katella High School, co-sponsored with another council member. 02:48:10
  • A council member noted coming changes to health care for Medi-Cal recipients after the first of the year as a reason to attend the fair. 02:48:10
  • A council member reported that overnight repaving of Beach Boulevard is complete and thanked nearby residents. 02:49:52
  • A council member urged residents concerned about immigration enforcement to check the city's Contigo web page for updates. 02:51:14
  • A council member said there had been reports of four separate immigration enforcement incidents that day. 02:51:14
  • Natalie Rubalcava (Council Member, District 3) noted the city has only one public pool and voiced hope for a public-private partnership with the YMCA to add one. 02:58:34
  • Natalie Rubalcava (Council Member, District 3) described two replica mummies on loan from Guanajuato, Mexico, now rotating through city facilities including the public library. 02:59:39

Write to the City Council about this

City Manager's update

Staff announced the Veterans Day ceremony, the annual Anaheim Health Fair, utility and library awards, and sandbag stations ahead of rain. 03:09:01

  • The Deputy City Manager announced the twentieth annual Anaheim Health Fair at the Convention Center on November 14, open to all regardless of insurance or immigration status. 03:09:11
  • The Deputy City Manager congratulated Anaheim Public Utilities on a Smart Energy Provider designation. 03:09:11
  • The Deputy City Manager reminded residents and businesses of self-fill sandbag stations ahead of expected rain. 03:10:18

Write to the City Council about this

Consent calendar

Streets and public works

The council approved routine items in one vote, including consultant contracts, a storm drain screen contract, an annexation application, two shuttle franchise applications, and a license extension for a tire shop on city property on West Lincoln Avenue that drew criticism in public comment. Items 3, 7 and 12 were pulled for separate votes. 03:11:43

  • Motion to approve the balance of the consent calendar (items 1, 2, 4-6, 8-11, 13-15), mover and seconder not identified; Natalie Rubalcava (Council Member, District 3) recused on item 8. Result: passed, 7-0. Recused: Natalie Rubalcava (Council Member, District 3). 03:12:58

Write to the City Council about this

Employment agreement for new City Manager Item 3

Appointments and leadershipPay and pensions

The council approved a contract appointing Jonathan Borrego as City Manager, effective December 28, 2026, filling a vacancy that opened in February. Staff said the appointee spent 29 years working for Anaheim and now runs Oceanside; the contract sets a $409,000 salary and severance that starts at 12 months. 03:13:23

  • Motion to approve the employment agreement for the City Manager appointment (mover and seconder not identified). Result: passed, 7-0. 03:18:44
  • The Human Resources Director said a nationwide search by the firm CPS HR drew about 160 candidates, with the council interviewing finalists from California and out of state. 03:14:47
  • The Human Resources Director said the appointee currently serves as city manager of Oceanside. 03:14:47
  • The Human Resources Director noted the appointee previously worked 29 years for Anaheim on projects including the Platinum Triangle vision and the Packing District. 03:15:47
  • The Human Resources Director outlined terms: a $409,000 salary and severance of 12 months for the first two years, dropping two months a year to a six-month minimum. 03:15:47
  • A council member said he pulled the item so the public could hear how the selection process worked. 03:17:11
  • A council member credited the executive team for keeping the city running during the vacancy and said he would support the appointment. 03:17:11

Write to the City Council about this

20-year solar-plus-battery power purchase from Heartland Solar 1 Item 7

EnergyClimate and sustainability
A map of the solar-and-battery project's site, on 2,362 acres of retired farmland about 30 miles southwest of Fresno.
A map of the solar-and-battery project's site, on 2,362 acres of retired farmland about 30 miles southwest of Fresno. Shown at the City Council, Nov 10 · 03:21:22

Anaheim Public Utilities will buy all output from a 150 MW solar and 138.5 MW battery facility in Fresno County for 20 years, at an annual average cost of $47,700,000 and about $955,000,000 over the term (agenda). Staff called it the largest project in the utility's portfolio, enough for roughly 75,000 Anaheim homes, and said it helps meet state mandates of 60% renewable power by 2030. It is paid by utility ratepayers, not the general fund; staff said it would not change bills in the near term. 03:19:22

  • Motion to approve the Renewable Energy Purchase and Storage Agreement with Heartland Solar 1, LLC (mover and seconder not identified). Result: passed, 7-0. 03:40:17
  • The acting Public Utilities General Manager said the project helps meet the state mandate of 60% renewable power by 2030. 03:19:36
  • The acting Public Utilities General Manager said a 2025 request for proposals drew 85 offers from 28 developers. 03:20:36
  • The acting Public Utilities General Manager said the plant will sit on 2,362 acres of retired farmland about 30 miles southwest of Fresno, away from high-risk fire zones and schools. 03:20:36
  • The acting Public Utilities General Manager said it would power roughly 75,000 homes, with construction starting March 2027 and operation by summer 2028. 03:21:39
  • The acting Public Utilities General Manager put the fixed-price cost at about $47 million a year, about $23 million for solar and $24 million for storage. 03:21:39
  • The acting Public Utilities General Manager explained the battery stores cheap midday solar power for use in the evening when demand and prices rise. 03:22:41
  • A council member noted the aggregate cost of more than $900 million over 20 years and asked how Anaheim compares with other utilities. 03:23:55
  • The acting Public Utilities General Manager said Anaheim is on track to meet the 60% renewable requirement while some others are not quite there yet. 03:24:25
  • A council member confirmed with staff that the cost comes from the utility's ratepayer-funded enterprise fund, not the general fund. 03:24:54
  • Public Utilities' assistant general manager of finance and energy resources said customers would see no change in reliability and the batteries would discharge at peak evening demand. 03:25:28
  • Natalie Rubalcava (Council Member, District 3) praised the utility and said residents avoid brownouts seen in cities served by Edison. 03:26:27
  • A council member asked whether the clean energy is also cheap and whether ratepayers would pay more. 03:27:26
  • Public Utilities' assistant general manager of finance and energy resources said customers' bills would not change in the immediate future because of the project, since a Utah power plant goes offline in June 2027 and this replaces it in the budget. 03:28:05
  • Public Utilities' assistant general manager of finance and energy resources said the power supply budget is about $310 million a year and not expected to change materially in the next couple of years. 03:28:05
  • Public Utilities' assistant general manager of finance and energy resources cautioned that future variable costs such as transmission can't be predicted. 03:28:41
  • Public Utilities' assistant general manager of finance and energy resources said the plant's expected capacity factor is about 32%, with the battery adding about four hours a day. 03:29:27
  • Public Utilities' assistant general manager of finance and energy resources acknowledged a gas plant would likely be cheaper absent state rules, but new gas plants can't be built in California. 03:30:22
  • Public Utilities' assistant general manager of finance and energy resources explained that the city gets no renewable credit for its Hoover Dam share because state law excludes large hydropower. 03:31:25
  • A council member asked about environmental and fire risks of the battery facility. 03:32:11
  • The acting Public Utilities General Manager said Fresno County's environmental review considered fire hazard and flooding and approved the project. 03:32:42
  • Public Utilities' assistant general manager of finance and energy resources described performance guarantees: no payment for the battery if it falls below 90% of capacity for three straight months, and price differentials if solar falls below 80%. 03:33:38
  • Public Utilities' assistant general manager of finance and energy resources said the city would receive $350,000 per megawatt in liquidated damages if the project misses its completion date. 03:33:38
  • The acting Public Utilities General Manager said the city owns no part of the plant, so equipment failures are the owner's responsibility. 03:34:52
  • Public Utilities' assistant general manager of finance and energy resources said state waivers exist if the 60% target is missed, requiring council authorization, but staff has no intention of seeking one. 03:35:35
  • A council member voiced frustration with state mandates that leave the city carrying nearly a billion dollars in long-term obligation. 03:36:07
  • Natalie Rubalcava (Council Member, District 3) asked whether the state might roll back or extend the mandates under the new governor. 03:37:01
  • The acting Public Utilities General Manager said staff has seen no indication of a policy shift and continues to plan for electrification and load growth. 03:37:28
  • Natalie Rubalcava (Council Member, District 3) asked staff to consider lobbying Sacramento to relax the clean energy mandates. 03:38:01
  • The presiding officer asked, and staff confirmed, that the city is not building the plant, only buying its output for 20 years. 03:38:30
  • Public Utilities' assistant general manager of finance and energy resources said Anaheim is the sole buyer of the plant's power, though the contract could be assigned to partner agencies. 03:39:10
  • Public Utilities' assistant general manager of finance and energy resources said an approximately 18-megawatt landfill power project leaves the portfolio in 2036. 03:39:53

Write to the City Council about this

Resort-area shuttle franchise for Parking Company of America Item 12

Public transitEvents, film, and tourism
A shuttle bus. Parking Company of America has applied for a proposed non-exclusive franchise to run shuttle service in Anaheim's resort and Platinum Triangle districts.
A shuttle bus. Parking Company of America has applied for a proposed non-exclusive franchise to run shuttle service in Anaheim's resort and Platinum Triangle districts. Shown at the City Council, Nov 10 · 03:41:26

The council accepted an application from PCAM, LLC (Parking Company of America) for a non-exclusive franchise to run shuttles between Garden Grove hotels and the Disneyland Resort and Convention Center, replacing service lost when the ART bus system ended in March 2026, and set a public hearing for December 15, 2026. Staff described a two-year initial service, an $8 all-day fare with free rides for resort employees, and a proposed $2,000 annual franchise fee. 03:40:21

  • Motion to adopt the resolution of intention to grant a non-exclusive franchise to PCAM, LLC dba Parking Company of America and set a public hearing for December 15, 2026 (mover and seconder not identified). Result: passed, 7-0. 03:49:23
  • Public Works staff said the Anaheim Transportation Network ended its ART bus service on March 31, after which this operator began serving Garden Grove hotel guests. 03:41:39
  • Public Works staff said 10 participating hotels with about 3,378 rooms are served. 03:41:39
  • Public Works staff said fares are $8 for an all-day pass for ages three and up, with free rides for resort employees. 03:42:42
  • Public Works staff said six gas-powered ADA-compliant shuttles of about 24 seats will run for the first two years. 03:43:47
  • Public Works staff said any term extension would require the operator to switch to clean-fuel shuttles. 03:43:47
  • Public Works staff said the $2,000 annual fee is meant to cover the city's cost of processing and monitoring the franchise. 03:43:47
  • Public Works staff laid out the schedule: hearing December 15, ordinance adoption January 12, 2027, effective February 11, 2027. 03:44:48
  • Norma Campos Kurtz (Council Member, District 4) thanked staff for guiding resort hotels after the ATN shutdown. 03:45:55
  • Norma Campos Kurtz (Council Member, District 4) noted that items 12, 13 and 14 were tied together and that she pulled this one as the first of them. 03:46:32
  • Norma Campos Kurtz (Council Member, District 4) thanked staff for meeting with nearby residents and keeping shuttles off residential Walnut Street. 03:46:32
  • A council member stressed that ATN was a separate quasi-governmental agency, not city-operated, and asked whether the new operator's drivers are Teamsters. 03:47:47
  • City staff confirmed the drivers are Teamsters and that former ATN drivers were hired. 03:48:40

Write to the City Council about this

Deadline to amend or terminate the A-Town development agreement Item 16

Development projectsAffordable housing
An aerial view of the A-Town project site, including Areas B, C and D, where the remaining 132 residential units were planned.
An aerial view of the A-Town project site, including Areas B, C and D, where the remaining 132 residential units were planned. Shown at the City Council, Nov 10 · 03:51:58

Public hearing on the long-delayed A-Town project at 1404 East Katella Avenue in the Platinum Triangle (developer PT Metro, LLC, tied to Lennar). The council set July 31, 2027 as the termination date for the development agreement unless an amendment addressing its third and later performance milestones is adopted by then. Staff said the agreement locks in older rules, so newer affordable housing and in-lieu fee requirements don't apply unless added by amendment, and that a promised grocery store is part of the remaining negotiations. 03:50:03

▶ Hear it Does a long-stalled project escape the city's newer housing rules? · 0:51

  • Motion to adopt the resolution setting July 31, 2027 as the termination date for Amended and Restated Development Agreement No. 2005-00008 with PT Metro, LLC unless an amendment is adopted by then, with the environmental determination (mover and seconder not identified). Result: passed, 6-1. No: Ashleigh Aitken (Mayor). 04:02:44
  • The Planning and Building Director recounted that a 2015 revised agreement allowed up to 1,746 homes, 50,000 square feet of commercial space and two public parks. 03:50:36
  • The Planning and Building Director said the third milestone required 462 more homes, of which 132 remain unbuilt. 03:51:36
  • The Planning and Building Director said the developer had trouble financing large podium projects and did not pull building permits for the remaining units. 03:51:36
  • The Planning and Building Director said the developer missed a July 31, 2026 deadline to file a formal amendment application, leading to this hearing. 03:52:40
  • The Planning and Building Director said staff would return with an ordinance to terminate the agreement if no amendment is completed by July 31, 2027. 03:53:46
  • The presiding officer asked whether newer affordable housing rules and in-lieu fees apply or whether the developer is grandfathered by repeated extensions. 03:58:32
  • The Planning and Building Director answered that the newer in-lieu fee and affordable housing requirements don't apply unless amended into the agreement. 03:59:29
  • The presiding officer predicted the project would show no progress by July 2027. 03:59:56
  • The presiding officer argued the city should stop letting developers extend agreements far into the future without keeping up with rising fees. 03:59:56
  • The Planning and Building Director said staff is making one final push for a deal that brings Platinum Triangle residents a grocery store, since the property can't stay tied up without one. 04:01:13
  • Natalie Meeks (Council Member, District 6) said she would support the item because the agreement ties the developer to a grocery store she considers critical for the area. 04:01:54

Write to the City Council about this

Closed session report: a lawsuit settlement on emergency shelters Item Closed Session 3

Lawsuits and settlementsHomelessness

The city attorney's office reported that in closed session the council approved a settlement in a lawsuit against the County of Orange and others that places requirements on existing and future emergency shelters, with no money paid by the city. Nothing was reported on closed session items 1 and 2. 04:03:26

  • Closed session vote, with Natalie Rubalcava (Council Member, District 3) and Norma Campos Kurtz (Council Member, District 4) absent, to approve a settlement, in a lawsuit against the County of Orange and others, that places requirements on existing and future emergency shelters. Result: passed, 5-0. 04:03:32

Write to the City Council about this

Council agenda setting

PolicingTrash and recyclingSeniors and disability

Council members asked staff for future reports on permit streamlining, senior facility needs, the police mounted unit facility, a landfill strike's effect on trash pickup, vacant parcels, and police overtime. 04:03:53

  • Natalie Meeks (Council Member, District 6) requested an update on the permit streamlining task force, including processing-time statistics. 04:04:11
  • Natalie Meeks (Council Member, District 6) asked community services staff for a workshop or report on the senior needs assessment and options and costs to meet it, as bond payoffs free up money for capital projects. 04:04:11
  • A council member requested a timeline for the police mounted unit facility, for which donated money was accepted. 04:05:43
  • Natalie Rubalcava (Council Member, District 3) requested a memo on possible trash pickup disruptions from a landfill strike. 04:06:32
  • Natalie Rubalcava (Council Member, District 3) requested a memo on vacant parcels, citing lots on Anaheim Boulevard with encampments and trash. 04:06:32
  • The presiding officer asked for a future agenda item with the police department on the overtime issue and actions taken since it began under the prior chief. 04:07:14

Write to the City Council about this

Adjournment in memory

The meeting was adjourned in memory of a retired Marine master sergeant who was chaplain of American Legion Anaheim Post 72, the first Mexican American judge on the Orange County Superior Court, and a co-founder of the United Farm Workers. 04:07:39

Write to the City Council about this

Public comment

  • The clerk announced 15 in-person speakers for general public comment, though about 20 spoke; one spoke on an agenda item, one spoke remotely, and the clerk reported eight written comments.
  • About eight speakers, several identifying themselves as relatives, called for justice in the death of a 19-year-old who, speakers said, was shot by Anaheim police on December 6, 2025. They demanded release of the autopsy and unedited footage, and some alleged ongoing police harassment of the family. One speaker said they would return December 8 near the anniversary.
  • Several speakers criticized the mayor over allegations of drinking and of racial and homophobic slurs, and some called for her resignation. One speaker said they sympathized with addiction but objected to joking about it.
  • Several speakers criticized police union campaign spending supporting a council member's reelection, the roughly 16-17% police raises, and overtime at Disneyland. One speaker called for that council member and the mayor to resign.
  • Three speakers objected to consent item 8, the JR Wheels & Tires license on city property, as far below market rent and asked that it be discussed publicly. One said the business had donated to a council member's campaign.
  • Several speakers raised spending accountability, asking for audits of purchasing and city credit card spending, public disclosure of outside investigation and legal costs, and controls before an expected windfall from paid-off resort bonds.
  • The one speaker on agenda items asked the council to create safe parking for homeless people living in vehicles, citing a petition with more than 100 signatures. Another speaker urged council members to feed the unhoused year-round.
  • A shelter resident recovering from a hit-and-run asked how long it takes to get housed in Anaheim and criticized a recuperative care provider and the police investigation.
  • One speaker criticized delays in the Angel Stadium property condition assessment, approved in 2023 for $325,000, and cited a 2025 state audit of the stadium lease.
  • One new resident described car break-ins and vandalism in a county island near Ball Road and asked why the sheriff serves the area. The mayor explained the county island and staff took their information.
  • Other speakers read scripture, honored Native American veterans and code talkers, commented on the election results, recited a Christmas poem, and congratulated reelected council members.

What's next

  • Next regular council meeting is Monday, November 16, 2026, not the usual Tuesday.
  • Public hearing December 15, 2026 on the shuttle franchises for Parking Company of America (item 12), Embassy Suites (item 13) and HMR Transportation (item 14). For the Parking Company of America franchise, staff said ordinance adoption would follow January 12, 2027, effective February 11, 2027.
  • The new City Manager's appointment takes effect December 28, 2026.
  • The A-Town development agreement ends July 31, 2027 unless an amendment is adopted. Staff said it would otherwise return with an ordinance to terminate it.
  • The Heartland solar and battery project is expected to begin construction in March 2027 and operate by summer 2028.
  • Staff reports or memos requested on the permit streamlining task force and the senior needs assessment (Natalie Meeks (Council Member, District 6)), the police mounted unit facility's timeline (Kristen Maahs (Council Member, District 5)), and a landfill strike's effect on trash pickup and vacant parcels (Natalie Rubalcava (Council Member, District 3)); and a future agenda item on police overtime (Ashleigh Aitken (Mayor)).
  • Natalie Rubalcava (Council Member, District 3) asked staff to consider lobbying Sacramento to relax state clean energy mandates.
  • Anaheim Health Fair Saturday, November 14 at the Convention Center.
  • The emergency access road funded by the $750,000 state grant is expected to be completed in about a year and a half.

Write to the City Council before its next meeting: publiccomment@anaheim.net

Every claim is checked against the recordings and documents linked above. Report an error · Transcript (WebVTT) · Download the MP3

Embed this episode

Paste this into a post on WordPress, Ghost, or any site that takes HTML. On WordPress, pasting this page's address works too.

<iframe src="https://anaheim.civic.fm/embed/episodes/2026-11-12" width="640" height="160" style="border:0;max-width:100%" title="Anaheim names a new city manager and approves a 20-year solar deal · Anaheim" loading="lazy"></iframe>